Skip to content
Date updated: 7/11/2024

At present, there are a number of major works projects underway that will repair and improve our estates. The City of London Corporation's Major Works Core Officer Group has been formed to ensure a consistent approach to communication, programming, and delivery of these works in line with the original vision for our estates and any listed requirements.

List of projects by estate

Current Projects 

Retrofitted Water Suppression Sprinklers Installation to the Point Blocks

The retrofit sprinklers project aims to install fire supressing sprinklers, and heat activated fire alarms inside all flats within East Point, Centre Point, and West Point to protect residents in the unlikely event of a fire. 

Each flat's sprinkler heads and pipes will be independent from each other and having block-wide installation will enhance the overall building safety. 

The majority of communal install has finished, however there has been a noticeable delay in final fittings due to the landlord awaiting sign-off from Southwark Council Building Control.  During the course of the sprinkler system installation works, our contractors United Living have managed to gain access into over 95% of properties in the three blocks on the Points. 

Please contact PPCR. if you have any questions relating to the Sprinklers project. 

Fire Door Replacement Programme (all blocks excluding Twelve Acres)

A programme of works to replace all front entrance doors, including communal corridor fire doors and fire escape doors. 

The lower level blocks on the estate are complete.  The Point blocks are ongoing, and we are experiencing some access issues, that we are working closely with the estate officers to overcome.  

On Harman Close, we have managed to replace the doors on the first floor, but the doors at ground floor level cannot be replaced until all services that penetrate the door frames have been removed, following the fire alarm and call line upgrade is complete by others. 

 

Future Projects

George Elliston and Eric Wilkins House - Replacement of Roof, Windows, and additional Works. 

The replacement of roofs and windows and external repairs to George Elliston and Eric Wilkins House. 

The principal designer, Studio Partington have  submitted a draft options appraisal for the scope of works and officers will be reviewing this with them.  Once the scope is agreed, a formal report will be put before Committee to develop the project further. 

Residents will be kept informed of how things are progressing and the range of works that are required.  All statutory, planning and tendering requirements will need to be factored into the timetable for works. 

Initial access may still be needed to some flats in order to help inform how things proceed, but residents will be advised if this is the case. 

MUGA (Ball Games Area) 

The renewal of the surfacing, fencing and facilities of the ball games area.

The City Corporation obtained a report on how trees are affecting the MUGA and what can be done to prevent future damage once facilities are renewed. Options need to be considered in the context of users’ safety, environmental concerns, and the current financial position. Further liaison with Southwark Council may be required to establish what may be done with regards to trees whose roots affect the surfacing and what can be done to mitigate this, in order to find the best overall solution.

Further to the above, the City Corporation have had the area looked at by leisure companies to assess possibilities for the area. Possible grant funding for the works will continue to be explored, and depending upon internal finances, officers may ask Committee to consider partial or full funding to bring the area up to standard. 

Current Projects

Fire Door Replacement 

A programme of works to replace all front entrance doors, including communal corridor fire doors and fire escape doors.

The installation of the new fire doors are now complete on the estate. 

Current Projects

Great Arthur House - Curtain Wall

Unfortunately, the outstanding issues of balcony door handles and brush seals, still need resolution. The City Corporation and John Robertson Architects are continuing to engage with Equans and other firms to try and reach satisfactory conclusions to these matters. 

Some repairs at roof level have been undertaken to address issues of water ingress unconnected to the curtain wall works. 

Window Refurbishment Programme and Associated Works

The refurbishment of window frames and installation of vacuum glazing, insulation of roofs/soffits and new ventilation systems across all blocks on the estate. 

There is a Resident Liaison Group for both Crescent House and the Wider Estate who meet on alternate months.  Summaries of the meetings are on the project website.

Crescent House 

The Contract will be procured under a two stage tender process. Stage 1 evaluations have been completed and the Stage 2 documents are under review. The windows contractors who successfully completed work on the Pilot Flat for both the aluminium and wooden windows are named sub-contractors. This will ensure that we retain the high standard already set. 

Work to discharge the planning conditions continues. 

Wider Estate

Early in October the Project Team held a drop-in session to present outline designs to residents and a further drop-in session will be arranged for early January to present the detailed designs. Submission of planning application and listed building consents is anticipated for January/February 2025.

Great Arthur House Retrofitted Water Suppression Sprinklers Installation

The retrofit sprinkler project aims to install fire supressing sprinklers, and heat activated fire alarms inside all flats within Great Arthur House to protect residents in the unlikely event of a fire. 

Each flat's sprinkler heads and pipes will be independent from each other and having block-wide installation will enhance the overall building safety. 

Adjustment to Great Arthur House programme has been scheduled to merge the objectives of this project with the planned fire door and compartmentation project to create one fire safety package project. We will keep you updated on further information. 

Please contact PPCR. if you have any questions relating to the Sprinklers project. 

Great Arthur House - Fire Safety

All residents of Great Arthur House will have received a letter with the latest updates on the fire safety works with the following information.

Important notice - Fire Safety Works - Fire Alarm - To maintain integrity of the fire alarm system and to prevent unnecessary activation:

  • Do NOT paint or cover the detector.
  • Do NOT tamper with the detector.

The detectors will require annual maintenance including inspections. Should there be a fault or if you have any queries or concerns, please contact the Estate Office on 020 7253 2556.

A reminder that smoking in communal areas is prohibited and that smoking within the flats, especially near the detector, may trigger the alarm. 

A functional fire alarm has been installed and set as a phase evacuation, where the fire alarm activates from the two floors above and one below will evacuate the building, and the remaining floors will receive an intermittent beep to standby.

Should any resident have questions about the alarm system, including the evacuation process, please contact the Estate Office.

Great Arthur House - Fire Door and Compartmentation

Fire compartmentation works and installation of Fire Doors to meet statutory requirements as laid out in Part B of the Buildings Regulations 2010.

This project is currently on hold as the scope of this project will be driven to a large extent by the works being undertaken on the sprinkler project. We are continuing to engage across both projects as we proceed.

The brief/scope of the Fire Compartmentation project will be developed further as the Sprinkler project progresses, and we will continue to keep you updated. Please keep an eye on the notice boards and Housing Major Works website for further updates on the Fire Compartmentation project.

Heating - Crescent House and Cullum Welch House

The installation of communal heating and hot water to residential properties.

The installation of the communal heating and hot water to residential properties will not be progressing in the immediate future. Properties will remain on individual heating systems for now.

Lighting, Signage and Accessible Routes

Upgrade of the existing communal external lighting provision to modern, energy-efficient fittings. 

This project has currently been paused but essential repairs should be reported via our repairs team. 

COLPAI

Contractors ISG are currently on-site undertaking construction works to deliver 66 new social homes and a new primary school. As a local authority, we are committed to smart, safe, and motivated working. During these difficult times, we must ensure that we operate 'Business Continuity'. This means having a robust plan in place in order to keep moving forward, contribute to the economy, keep our workforce mobilised and ensure we are in the best possible position to deliver for the local community.

Please note that approval allowing residents to move into the building is delayed because we need to fix an area of brickwork on the western side, located behind the balconies. 

We are currently discussing when and how to resolve the issue, and whether new residents can move in before or during the planned work. 

We will keep you updated with the latest information and a schedule for the repairs once it has been confirmed. 

Construction Activities

Please be aware that ISG will not maintain a daily management presence on site, at least until remedial actions have been agreed upon. 

Working Hours

The consented working hours are: 

  • Monday to Friday - 8am to 6pm
  • Saturday - 9am to 2pm

The consented reduced impact hours are:

  • Monday to Friday 10am to 12pm and Saturday 2pm to 4pm.

During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery. 

On-Site Security

  • Security guard on-site full time 7am - 6.30pm

KEY CONTACTS For site emergencies, please contact:

John Macleod, T: 07816 337 792

Pui Wong, T: 07866 988 932

For general enquiries, please email the COLPAI Project Team or call 0800 772 0475

Please visit our COLPAI monitoring data to view monthly monitoring data results. The monitoring data is also available on the site noticeboard.

You can view the progress with images from taken from site.  

We would encourage everyone to opt-in to the digital newsletter by visiting our project website or emailing the COLPAI Project Team to ensure we are able to stay in touch should physical distributions become unsustainable.

Future Projects 

Fire Door Replacement Programme (All blocks excluding Great Arthur House) 

A programme of works to replace all front entrance doors within City of London Corporation Housing Managed residential blocks of flats, the replacement of any communal corridor fire doors and fire escape doors from flats with fire doors that give up to 60 minutes fire resistance (30 minutes as an absolute minimum where 60 minutes is not achievable).

Procurement for the Fire Door Replacement Project is underway at several other Estates. A measured survey for the doors to be replaced at Golden Lane Estate, will be scheduled in due course ahead of the formal design process required to satisfy heritage constraints. 

CCTV

Officers have been asked to look into the possibility of widening the CCTV coverage on Golden Lane Estate.  This is at a very early stage and will depend on the availability of finance and necessary listed building consents being met.  Residents will be kept further informed as and when this project develops. 

Current Projects

There are no current projects active on Holloway Estate. 

Current Projects

Communal Heating System Improvement Works

The City Corporation were successful in obtaining grant funding from Central Government and the Climate Action Strategy for improvements to the communal heating system at Isleden House.  These include new heat interface units within properties, new thermostatic radiator valves, improvements to the controls of boilers and individual heat meters. 

FairHeat have been appointed to design the scheme and are progressing with surveys.  It is hoped that the initial designs will be submitted to officers for consideration by late summer. 

A 'Meet the Contractor' event for Isleden House residents will be held on Wednesday 13 November 2024  at 5pm in the Community Room. 

Current Projects

Communal Heating / Cold Water Distribution System Replacement

The replacement of current heating system with modern facilities and a programme of control activities, repair and replacement works to water supply systems for which the City Corporation is responsible across Housing Revenue Account Estates. This includes communal hot/cold water storage tanks, communal pipework, individual hot/cold storage tanks and pipework in tenanted properties, hot/cold water tanks and pipework in estate offices.

There are still five properties in Petticoat Tower that require the installation works, these properties are refusing access, as a result we are still unable to isolate and decommission the old existing system, which is causing some noise to other residents.  This matter is currently in the hands of the legal department.  Works are progressing well in Petticoat Square. 

Where there have been no engagements, we are working with our colleagues in the estate office. 

We are now commencing consultation with residents to discharge the remaining planning conditions. 

If there are any issues, residents can contact TSG using the usual repairs line 0800 035 0003 or you can email TSG.

Play Area Refurbishment - Middlesex Street Podium

The company which provided and installed the original artificial grass surfacing returned to site to carry out heavy sanding of the area.  They have also visited four other sites which are experiencing the same issues and have tried a range of solutions to try and resolve the static problems permanently.  These are being monitored to judge the effectiveness of the solutions and we will advise residents further once we have been able to assess the next course of action.  However, we do continue to ask all residents who experience shocks to make sure that they report these to the estate office, especially during summer months when the static issue is more prevalent.  

Petticoat Tower Retrofitted Water Suppression Sprinklers Installation

The retrofit sprinklers project aims to install fire supressing sprinklers, and heat activated fire alarms inside all flats within Petticoat Tower, to protect residents in the unlikely event of a fire. 

Each flat's sprinkler heads and pipes will be independent from each other and having block-wide installation will enhance the overall building safety. 

Work progress so far :- 

  • 17 flats have been fully completed with sprinklers and fire alarm works.  
  • The UPS commissioning is completed. 
  • Pressure testing from the basement has been completed. 
  • More bookings for flats to have full installations. 
  • Evac Panels are wired up. 

Harmony is planning to have a reduced presence on site to utilise their resources and time more efficiently.  From now on Harmony will carry out block booking appointments only. 

When booking an appointment with Harmony, it will be essential that they can access your home for all three days required for the installation works. This is to ensure the newly installed sprinkler system can be tested and commissioned.

We have added an additional questions and answers information leaflet on the retrofit sprinklers, following our 26 April 2022 webinar.  

Please contact PPCR. if you have any questions relating to the Sprinklers project. 

Petticoat Lane Market Project

As part of the Petticoat Lane project that City of London Corporation carried out, in partnership with London Borough of Tower Hamlets(LB of Tower Hamlets), works to the northern part of Middlesex Street at its junction with Bishopsgate and to the west pavement along the Middlesex Street Estate. 

Seating and additional greening was also installed in the pavement outside the Middlesex Street Estate to complement the new street trees. 

LB of Tower Hamlets team are now preparing proposals for Petticoat Lane Heritage Trail that will depict the diverse community and history of Petticoat Lane through installations of plaques or similar throughout the area. 

You can find out more information on the project at Give My View.

If you would like more information or have any questions about the project email the Policy and Projects Team.

Middlesex Street Area Enhancements - Artizan Street Landscaping Project

If you have questions regarding progress, please do not hesitate to contact the Project Manager at City Public Realm.

Outdoor Leisure Facilities

If you have questions regarding the progress of the outdoor leisure facilities, please do not hesitate to contact the Project Manager at City Public Realm

Future Projects 

Concrete Repairs

This project is on hold due to expenditure review. The design, specification and estimate costings have been completed.

Current Projects

Window replacement including Redecorations (Sumner Buildings, Stopher House and Pakeman House)

Window renewal and internal/external common parts redecorations across multiple estates. 

Work Progress: 

Sumner Buildings

Balcony doors are being delivered over the next couple of weeks for properties 1-30 Sumner Buildings and balcony doors are now being produced for flats 31-50.  We have renewed several balcony doors from flats 1-30 which can be seen from the courtyard. 

We have completed window renewals in flats 1-30, 31-40, and are finishing 41-50.  Properties at 51-60, 61-70, 71-85 and 86-100 Sumner Buildings are all being worked on simultaneously as we have passed 50% completion.  External mastic around all the windows on all blocks are ongoing.

Stopher House    

Despite the delays with some window production, we have now completed window renewal on properties between 48 and 60 Stopher House and have now moved onto some of the lower numbered flats. We will be in contact with every resident once their windows have been produced to arrange for a convenient date to renew their windows. 

Pakeman House

All windows and drying room doors have now been installed at Pakeman House, and we are glad to report this part of the project has been a huge success.  We are in the process of rectifying any issues with installation and final decorative works, please contact Matthew Jonas if you have any enquiries or outstanding works to be completed.  External mastic is still ongoing as well as internal and external decorating.  For keys to the drying rooms please contact the office at Pakeman House. 

We have now completed the works to the dormer windows and proceeded with the scaffold removal on the 4th floor walkway between flats 45 to 50 Pakeman House, this was removed on Thursday 25 and Friday 26 July 2024. 

We apologise for any disruption and for any inconvenience that may have been caused. 

Please remember all barriers and warning signs are for public safety and must not be ignored or moved. 

All other scaffold dependant works are due to be completed once works have been approved and signed off by the City of London Corporation. 

We thank you for your continued cooperation and we will endeavour to lessen any inconvenience and keep disruptions to a minimum amount of time. 

Decoration works (all estates)

Decoration works across all estates are nearly complete with just a few items, such as painting of shed doors that is set to commence over the next couple of weeks.  If you are leasing a shed, we ask that you provide us with a key so as these works can be completed.  Please contact ETEC RLO, Matthew Jonas, to arrange for access to your shed. 

Sumner Buildings: 87% internal and external decoration works completed. 

Pakeman House: 90% internal and external decoration works completed. 

Stopher House: 90% internal and external decoration works completed. 

Emergency Contacts:

If there is a breach of security the alarms have manned emergency call out so a guard will attend, further issues the residents can call the numbers below.  For other issues please contact the site manager first.

Sumner Buildings

Scaffold alarm emergency call-out / Strong Guard Security / 0800 612 0749.

Site Manager/ Ian Bedneau / 07842 001 956 

Pakeman House and Stopher House

Scaffold alarm emergency call-out / Panthera Group / 0845 165 1234.

Site Manager/ Ian Bedneau / 07842 001 956 

If you have any further queries in the meantime, you can contact the Major Works Team

Fire Door Replacement Programme (all blocks excluding Horace Jones House)

A programme of works to replace all front entrance doors within the City Corporation Housing managed residential blocks of flats, the replacement of any communal corridor fire doors and fire escape doors from flats with fire doors that give up to 60 minutes fire resistance (30 minutes as an absolute minimum where 60 minutes is not achievable).

Work is progressing well at Sumner Buildings, there were two properties outstanding to complete the project, access has now been granted to the two properties for completion of the project.  

Future Projects 

Concrete Testing and Repair

A concrete testing contract was procured to assess the current condition of the pre-cast concrete elements on the Southwark Estate blocks and to make any repair recommendations. A concrete repair contract will follow to remedy the defects noted.

Concrete Repairs at Southwark Estate have been postponed and will not commence until the window project renewal is completed. Concrete repairs start date Summer 2024. 

Current Projects

There are no current major works project on Sydenham Hill Estate.

If you have any further queries in the meantime, you can contact the Major Works Team

Future Projects

Fire Door Replacement Programme

A programme of works to replace all front entrance doors within the City Corporation Housing managed residential blocks of flats, the replacement of any communal corridor fire doors and fire escape doors from flats with fire doors that give up to 60 minutes fire resistance (30 minutes as an absolute minimum where 60 minutes is not achievable).

Procurement for the Fire Door Replacement Project is underway at several other Estates. A measured survey for the doors to be replaced at the Sydenham Hill Estate will be scheduled for later in the year.

Future Projects

Windows Programme (including redecorations) 

Window renewal and internal/external common parts redecorations across multiple estates. 

The design team brief is near completion and the tender for the services of the design team is expected to go live early November 2024. Once the tenders have been evaluated and the successful bidder identified, we will be undertaking statutory post tender section 20 consultations with leaseholders. 

Subject to a successful tender and section 20 consultation, once appointed the design team will be working alongside the project team undertaking pre-planning advice ahead of submitting a new planning application. While the planning applications are underway the design team will also be working alongside the project team drawing specifications to re-tender for the works, which will also be subject to the statutory pre and post tender section 20 consultations with leaseholders. 

Subject to successful statutory consultations, tenders, planning consents and further committee approvals, the works are expected to start early to mid 2025.

Fire Door Replacement Programme 

A programme of works programme of works to replace all front entrance doors within the City Corporation Housing managed residential blocks of flats, the replacement of any communal corridor fire doors and fire escape doors from flats with fire doors that give up to 60 minutes fire resistance (30 minutes as an absolute minimum where 60 minutes is not achievable). 

Gerda who have been contracted to install the fire doors have almost completed the installation of the doors. There is one outstanding residential property, which we are currently working with our colleagues in the estate office to arrange for the works to be completed. 

There are also some of the communal doors still to be replaced, these required special testing, due to their unusual shape.  This has now been completed and they are now in fabrication, and will be installed in due course. 

Current Projects

There are no current projects active on Windsor House.

Future Projects 

Fire Door Replacement Programme

A programme of works to replace all front entrance doors within the City Corporation Housing managed residential blocks of flats, the replacement of any communal corridor fire doors and fire escape doors from flats with fire doors that give up to 60 minutes fire resistance (30 minutes as an absolute minimum where 60 minutes is not achievable). 

Procurement for the Fire Door Replacement Project is underway at several other Estates. A measured survey for the doors to be replaced at Windsor House will be scheduled for later in the year.

Current Projects

Communal Heating

Replacement Heating System for three larger blocks on York Way Estate. 

All works have now been completed for the communal heating. 

Any further queries regarding the heating works, please contact TSG repair line. 

New Development of 91 Homes

The City Corporation has entered into a construction contract with Higgins PLC to develop 91 new homes at the York Way Estate, alongside new landscaping and play spaces, a new Community Centre and a new Estate Office. 

Site Progress

Block A - Swaledale House – Concrete frame complete.  Infill light gauge steel framing system in progress.  Window installation, internal blockwork, scaffold erection and main staircase handrail in progress.

Block B - Herdwick House – Precast concrete balcony & columns in progress.  Infill light gauge steel framing system in progress.  Window installation, internal blockwork, scaffold erection and main staircase handrail in progress.  

Block C - Ryeland House – Precast concrete stairs installed from lower ground to second floor.  Third floor slab in progress.  Shear walls and verticals to level 2 compete.  Splash course brickwork complete. 

Block D - Aberdale House – Upper floors concrete slab complete.  Ground floor beam & block flooring complete.  Precast concrete stairs installed.  Infill light gauge steel framing system in progress.  Window installation and scaffold erection in progress. 

Noise, dust and vibration are constantly monitored across the site, to ensure levels do not exceed limitations. 

If you have any concerns or questions about the development, please contact the Resident Liaison Team in-person Monday to Friday in the Resident Liaison Office & Respite Centre or email them at York Way-Higgins or call Ruzi Bibi on 07773 540 602.

Please continue to check the York Way Estate website for updates.

 

Future Projects

Corridor Lighting and Redecoration of Internal Common Spaces

Project Briefing document completed and awaiting approval from Housing Programme Board.

Ventilation

Looking at the options for upgrade/replacement of the existing ventilation system. 

If residents have any issues with regard to the ventilation within their homes, these should continue to be reported through the repair system. The ventilation issue is to be considered as a future project, subject to need, and the necessary approvals being granted. 

Play Area Refurbishment

To update equipment within the play area.

This project is on hold as future play facilities are to be considered as part of the redevelopment works at York Way estate.

Fire Safety

Home visits and fire alarm fitting

The Fire Brigade currently deliver free Home Fire Safety Visits every year and with the visits they will also fit fire alarms in all areas where fires can start, including bedrooms and living rooms.

The London Fire Brigade now provide specialist alarms for deaf people/people with hearing impairments. They can provide standalone alarm systems and replacement alarm heads for bellman systems as part of a Home Fire Safety Visit. The alarms are free of charge and are fitted as part of the Home Fire Safety Visit.

If you are interested in receiving a visit from the London Fire Brigade or would like further information on the fire alarms, please call Freephone 0800 028 4428 or email the Fire Brigade.

Housing Fire Safety

Residents are able to view Fire Risk Assessments (FRAs) and Frequently Asked Questions (FAQs) for all of the City Corporation estates from the Housing Fire Safety web page.

Leaseholder Payment Options

The City Corporation recognises that it can be difficult for some leaseholders to pay for the cost of major works to their property in one go. We therefore have several ways to support you with this. To view the latest guide to the payment options for leaseholders take a look at the Leaseholder Payments booklet under the heading 'supporting information'.

Supporting Information

York Way Estate Construction Site Plan (111KB)
A construction site plan showing the location of each development block on the York Way Estate.
Date submitted: 13/07/23
Great Arthur House Sprinkler Q and A
Great Arthur House questions and answers information booklet.
Date submitted: 30/06/22
Petticoat Tower Sprinkler System Information PDF (700KB)
Date submitted: 12/07/21
Petticoat Tower Sprinklers FAQs PDF (650KB)
Additional questions and answers for Petticoat Tower Sprinklers
Date submitted: 30/05/22
Petticoat Tower Retrofitted Water Suppression Sprinklers FAQs PDF (200KB)
Date submitted: 8/06/21
FAQ's Window Projects General - Windsor PDF (176KB)
frequently asked questions on the windows project for Windsor House
Date submitted: 9/11/22
FAQ's Window Projects General - Southwark PDF (272KB)
Frequently asked questions on the window project for Southwark Estate.
Date submitted: 9/11/22
Leaseholder Payments PDF (450KB)
Date submitted: 23/12/19